1) Call to Order Mayor Anderson called the meeting to order at 3:02 p.m.

2) Discussion Item(s) a. Strategic Planning/Capital PlanningDiscussion Mayor Anderson said that this a continuation of the discussion and review of the 5-year plan. He noted that non-recurring projects currently in the 5-year plan result in a funding deficit of approximately $39 million and suggested either reducing the expenditure and/or pushing the project out to 6-25-year(long-term) plan. The following options close the funding gap were offered:

Progress Point • Reduce depending on final plans (Mayor) • Remove preparation of building pad ($750k) and arrival court ($1M) and include in the RFP. (Cooper) • Reduce by $3-4M. (DeCiccio)

Land – on Fairbanks near Denning ($3M) • Remove. (Cooper) • Take out $700k-$800k out and use to purchase other Fairbanks Avenue property to add to park land and own Lake Rose for stormwater management. (Weaver) • Remove. (DeCiccio)

Tree Farm • Move to long-term plan. (Mayor) • Remove $5M and reserve 2.5 acres to be used as post office distribution center, a new fire station or as lay-down for hurricanes. (Cooper and agreed to by Sullivan) • Remove. (DeCiccio)

Old Library • Reduce depending on determination of future use. (Mayor) • Explore public/private partnership and remove $7.5M and fix the roof and then use the ARPA funds to do renovations. (Cooper) • Leave $300k for maintenance. Move $7.5M out beyond five-year plan. (Weaver) • Investigate a property swap with Rollins (Sullivan) • Leave $800k until future of building is known and put on long-term plan. (DeCiccio)

Maintenance facility at Swoope ($800k) • Remove, can be a public/private operation. (Weaver)

Traffic Enhancements • Move $1.25M to long-term ($750k funded from ARPA) (Mayor and DeCiccio)

Bike and Mobility Plan (excluding ProgressPoint) • Remove additional $1M. Mayor Anderson said he believes some carry-over funds are included but will reconfirm. (Cooper) • Pedestrian Bridge along Sunrail at 17-92 ($1M) – Remove. She would like ProgressPoint connected with Sunrail first and then OAO connected to the CBD and would defer first to getting crossover on Fairbanks at Denning and on 17-92 at Morse. (Cooper) • Pedestrian/bike bridge alongside Sunrail ($1M) – Retain, suggested a tunnel rather than a bridge as it is less costly. (Weaver)

Lakemont “complete street” ($8M) • Move to long-term or consider for infrastructure bill funding. (Mayor) • Reduce to $3M for aesthetic improvements. Mayor Anderson suggested moving it to the long-term plan. Commissioner Cooper agreed. • Reduce from $8M to fund roundabout at Glenridge and bike paths on Lakemont ($2.5M) (Weaver) • Move to long-term. (DeCiccio)

Lakemont/Aloma Intersection ($3M) • Suggested a placeholder for improvements but push it into the long-term plan and not allocate general funds but instead look for getting it into the Metroplan slot or an infrastructure bill. (Mayor)

Glenridge Intersection ($1.239M) • Supports study for roundabout at Lakemont. • Remove until studies are completed (DeCiccio)

East/West Intersection at Denning/Fairbanks ($3M) and Westbound Morse at 17-92 ($4) • Remove until studies are completed. (DeCiccio)

Infrastructure Bill Prep – design and studies $500,000 • Partial amount for bike lanes on Lakemont. (Weaver)

Orange AvenueTraffic Improvements ($1) • Leave in five-year plan. Should be a budgeted item provided there is shared cost. (Weaver)

Orange/Denning/Minnesota roundabout ($4M). • Move out to long-term or consider for use of Federal infrastructure funding. (Mayor) • Need to put in mobility fee in place to cover. (Cooper) • Remove. (DeCiccio)

Parking Garages ($8M) • Move to long-term. Need for city facility (city hall). Should be a shared cost. (Weaver) • Move to long-term plan. (DeCiccio)

Central Park Stage ($1.3M) • Reduce to $500k. (Cooper) • Reduce by ½ since there are no restrooms. (Weaver)

WP 9-Hole/Swoope Maintenance Facility ($800k) • Add lightening shelter (DeCiccio)

Additional land park space ($5M) • Move to long-term. (Mayor)

Killarney Annexation (Fire Station) • Put money in for building but not land. (Staff to provide cost) (Mayor)

Fire Training Facility($550k) • Remove. Should be regional effort.(Cooper)


Charging Stations ($100k)

• Remove. Private market will do it. (Cooper)


City Hall ($12.5M)

• Reduce by $5M. Use remaining amount for interior upgrades to city hall. (Use $8M in CRA funds for a parking garage with retail component for the post office.) (Cooper)

• Reduce to $2M for AC and energy saving improvements (Weaver)

Commissioner DeCiccio said she feels there needs to be a plan for staffing due to the vacancies which include consideration of increasing salaries.

Mayor Anderson readdressed and discussion was held on the following:

• Central Park Stage - no full consensus on budget and asked whether the city should

$1.3M until the design is complete. Mr. Knight said he was just notified that the design has been received with a budget is in the area of $900k.

• Sufficiency of the infrastructure bill prep – suggested increasing the budget to $750k for studies of roadway intersections, pedestrian bridges, and bike and mobility paths.

• Progress Point ($3.5) – He feels it should be left at $3.5M. Discussion followed on cost and consultant estimates. Commissioners Cooper,Sullivan and DeCiccio agreed. He suggested an additional $1M. Need a healthy margin of error for self-managed work and added as placeholder for next discussion.

• Howell Branch – will add to list but will be funded by grants.

Commissioner Cooper suggested that staff take the $16M page from ACi and change the numbers on that page so we can see how we got from that number to the current number.


The meeting adjourned at 5:58 p.m.